April 26: Holes for footings in the courtyard. These will support the
trellis and the shed roof over the entry area. The courtyard is now nicely
visible.
 |
April 26: Overview from the northwest. Coutyard footings are clearly
visible an the rest of the entry area is taking shape.
 |
April 26: View over the greatroom. The shape and elevation changes
are now really visible.
 |
April 30: Mary standing in front of the HUGE beams that wil become
the greatroom. Those are 8x20's 32 feet long. Wow!
 |
April 30: Old nail (or maybe bullet?) holes in the beams.
 |
April 30: Footings for the trellis.
 |
April 30: View across the greatroom, getting filled in.
 |
April 30: Bedroom almost taking shape.
 |
April 30: Forms for the retaining wall outside the greatroom. Also
you can see the filling in to the west almost to the fiished grade.
 |
April 30: Dining area showing the inside and outside grades. Concrete
pillars on the outside are for the timber supports.
 |